Spearfish Creek Bore

Mainline Contracting Boring Project in South Dakota

PROJECT DESCRIPTION

Spearfish Creek Bore- at West Federal Street

Owner: City of Spearfish

This project will replace a segment of existing water main that has washed out across Spearfish Creek and can no longer be used.

A new steel casing will be bored though the rock underneath the creek bed, and a new water main installed to connect the existing water mains on each side of the creek.

This project is scheduled for a late Dec. 2014 completion.

Project Update: All underground work was completed by Dec. 14 and placed in service. The east and west sides of the creek received seed and mulch in Dec.

The restoration of the ponds was completed in March 2015.

Thank you to all of the residents for your cooperation with the work directly in your yards, and with the long hours and Saturdays that were worked on this project!